Screening | Domestic project |
Projects type: | |
Area: |
Constructed by HTPC and JTPCC
The project adopted two sets ZSC70240 (80T).
Constructed by SEPCOⅡ and HEPSEC
The adoption of one set ZSC80325 (120T) , one set ZSC60140 (50T) and one set ZSC70360 (140T).
Constructed by AEPC I
The project adopted one set ZSC80305(110T).
Constructed by HPCCⅠ and NEPCⅠ
This project adopted one set ZSC70240(80T) and one set ZSC70360(140T).
Constructed by SEPCC Ⅲ and SEPCC Ⅳ
This project adopted one set ZSC70240(80T) and one set ZSC65150 (50T).
Constructed by SEPCC Ⅱ and SEPCC Ⅲ
This project adopted two sets ZSC70240(80T).
Constructed by SEPCCⅠ
This project adopted one set ZSC70260(100T).
Constracted by TEPC
This project adopted one set ZSC70240(80T).
Constructed by Zhejiang Southeast Spaceframe Co.,Ltd
Construction area is 5700㎡.This project adopted one set ZSC50120(30T),one set ZSC3590(20T),one set ZSC5080(40T) and one set ZSC5580(30T).
Constructed by SCG
Construction area is 50000㎡.This project adopted one set ZSL50170(50T), one set ZSL1000(50T),one set ZSC30240(60T),one set ZSC22300(50T),two sets ZSC60200(60T).
Constructed by China Construction First Engineering Bureau Shanghai Zhongyi Construction Company
Construction area is 35000㎡.This project adopted one set ZSC1000(40T) and one set ZSC1400(40T).
Constructed by SCG
Construction area is 140000㎡.This project adopted four sets ZSL1000(40T).
Constructed by the 8th Bureau of CSCEC
Construction area is 146800㎡.This project adopted two sets ZSL750(50T).
Constructed by China Industrial Equipment Installation CO.,Ltd
Construction area is 194000㎡.This project adopted four sets ZSC70110(50T).
Constructed by SCG
Construction area is 230000㎡.This project adopted one set ZSC6090(30T),two sets ZSL750(50T),two sets ZSC6090(35T),four sets ZSL1100(40T) and two sets ZSL1200(60T).
Constructed by the 8th Bureau of CSCEC
Construction area is 230000㎡.This project adopted two sets ZSL750(50T).