Constructed by HNGC
Construction area is 270000㎡.The project adopted two sets ZSC70160(60T).
Constructed by Zhejiang Southeast Space Frame Company
Construction area is 340000㎡.This project adopted two sets ZSL1000(50T).
Constructed by Guangdong Installation Company
Construction area is 395000㎡.This project adopted one set ZSC6090(30T)
Constructed by the 8th Bureau of CSCEC
Construction area is 458000㎡.This project adopted two sets ZSC1100(50T),five sets ZSL1100(45T)and two sets ZSC300(16T).
Constructed by BCEG
Construction area is 680000㎡.This project adopted four sets ZSL1100(45T).
Constructed by the 2th Bureau of CSCEC
Construction area is 760000㎡.The project adopted one set ZSL750 (50T).
Constructed by the 8th Bureau of CSCEC
Construction area is 841584㎡.The project adopted eight sets ZSL1100 (45T).
Constructed by SCG and the 8th Bureau of CSCEC
Construction area is 1470000㎡.The project adopted five sets ZSL1200 (60T).
Constructed by SCG
The project covers an area of 116 hectares,and adopted one set ZSL380(32T).
Constructed by China 22nd Metallurgical Construction Corporation
Construction height is 48m,the project adopted one set ZSC60120(20T).
Constructed by Jianghua Company of China Construction First Building(group) Corporation Limited
Construction height is 100m,the project adopted one set ZSL1000(64T).
Constructed by Jiangsu Huning Mechanism Co.,LTD
Construction height is 120m, the project adopted two sets ZSL1000 (64T).
Constructed by the 8th Bureau of CSCEC
Construction height is 168m, the project adopted one set ZSL500 (32T) and one set ZSL260 (18T).
Constructed by SCG
Construction height is 180m , the project adopted two sets ZSL750 (50T).
Constructed by the 8th Bureau of CSCEC
The project construction height is 180m,and it adopted one set ZSC600(30T).
Constructed by BCEGC
The project construction height is 183m,and it adopted two sets ZSL380(32T).